Loading [MathJax]/jax/output/CommonHTML/jax.js
World Scientific
Skip main navigation

Cookies Notification

We use cookies on this site to enhance your user experience. By continuing to browse the site, you consent to the use of our cookies. Learn More
×

System Upgrade on Tue, May 28th, 2024 at 2am (EDT)

Existing users will be able to log into the site and access content. However, E-commerce and registration of new users may not be available for up to 12 hours.
For online purchase, please visit us again. Contact us at customercare@wspc.com for any enquiries.

Evaluating the project completion time when activity networks follow beta distribution

    https://doi.org/10.1142/S1793557121501102Cited by:1 (Source: Crossref)

    By using a recursive method, we determine the project completion time when the activity times are distributed according to a beta distribution. The kth moment of the maximum of non-identical independent random variables following this distribution-type is evaluated. Applicability and appropriateness of the beta model are illustrated by some examples, which show that the suggested estimate program evaluted and review technique of the project completion time is located between the lower bound estimate (PERT) and the upper estimate that was obtained by Kambarowski An upper bound on the expected completion time of PERT networks, Eur. J. Oper. Res.21(2) (1985b) 206–212. Moreover, this estimate gives less values of the approximation errors than most of the other known estimates.

    Communicated by B. K. Dass

    AMSC: 90B15, 62H10